求教下的各位,当初土地有斜坡。所以现在设计了公开室,当初到了site cut 的阶段,土质比想象中的硬,后果builder 告知咱们需求三个阶段,
大家好,对于名目遇到石头的问题,
要分三步做:
1. Extra cost for underground plumbing
2. Extra cost for excavation
3. Extra cost for concrete slab footing.
后果第一个阶段就说要额定9000刀,觉得builder 有点坑钱啊
第二,第三阶段,也只说预估,整个要20000出头点
现在签合同的时分,说过假如遇到额定的大石头,需求额定的费用,但只是说大略几百刀能够了,请各位看一下,请问公道吗
让builder 提供了大略第一阶段具体的清单
Please also find below cost break down for extra underground plumbing work:
Float for excavator for semi trailor truck to drop off and remove - 600.00 + GST
Rock breaker three days cost - 4,300.00 + GST
Qualified plumber to monitor operator and laser trench to correct depth and grade. - 1,十二0.00 + GST
Fill in trenches that will be widened by the rock breaker - 1,268.00 + GST
Charges to remove the rocks from site - 850.00 + GST
Total Cost for underground plumbing work - $8138 + GST
|
|